List of Infrastructure Project List of Infrastructure Project

This Report provides information on infrastructure projects implemented by the Government, either through traditional procurement mode or through Public Private Partnership (PPP) mode across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP)that were either under 'Pre-construction Stage', ‘Under Construction’ or ‘Operation and Maintenance Stage’ as on April 1, 2011 or ‘Awarded’ thereafter and with Project Cost >INR 5 crore; and.
  • Government Infrastructure Projects (Traditional Procurement): that were under 'Pre-construction Stage', or ‘Under Construction’ as on April 1, 2012 or ‘Awarded’ thereafter and with Project Cost >INR 50 crore.
Information available as on May 15, 2017
Please click on project name for more details of the project.
Search
No. of Projects in this Report: 7497 Total Project Cost(in Rs Crore): 4,322,880.19
Sl No
1 Implementation of rural electrification works in Vaishali under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 191.13 Energy Electricity transmission Under Construction North Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
2 Implementation of rural electrification works in Supaul under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 99.36 Energy Electricity transmission Under Construction North Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
3 Implementation of rural electrification works in Siwan under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 201.81 Energy Electricity transmission Under Construction North Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
4 Implementation of rural electrification works in Sitamarhi under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 193.62 Energy Electricity transmission Under Construction North Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
5 Implementation of rural electrification works in Sheikhpura under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 76.04 Energy Electricity transmission Under Construction South Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
6 Implementation of rural electrification works in Saran under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 195.47 Energy Electricity transmission Under Construction North Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
7 Implementation of rural electrification works in Samastipur under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 188.85 Energy Electricity transmission Under Construction North Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
8 Implementation of rural electrification works in Saharsa under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 158.28 Energy Electricity transmission Under Construction North Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
9 Implementation of rural electrification works in Rohtas under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 252.47 Energy Electricity transmission Under Construction South Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
10 Implementation of rural electrification works in Purnia under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 183.54 Energy Electricity transmission Under Construction North Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
11 Implementation of rural electrification works in Patna under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 322.39 Energy Electricity transmission Under Construction South Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
12 Implementation of rural electrification works in West Champaran under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 191.36 Energy Electricity transmission Under Construction North Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
13 Implementation of rural electrification works in Nawada under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 107.46 Energy Electricity transmission Under Construction South Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
14 Implementation of rural electrification works in Nalanda under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 162.57 Energy Electricity transmission Under Construction South Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
15 Implementation of rural electrification works in Muzaffarpur under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 103.14 Energy Electricity transmission Under Construction North Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
16 Implementation of rural electrification works in Munger under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 133.09 Energy Electricity transmission Under Construction South Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
17 Implementation of rural electrification works in Madhubani under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 225.96 Energy Electricity transmission Under Construction North Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
18 Implementation of rural electrification works in Madhepura under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 113.72 Energy Electricity transmission Under Construction North Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
19 Implementation of rural electrification works in Lakhisarai under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 97.76 Energy Electricity transmission Under Construction South Bihar Power Distribution Company Limited 18-Feb-2017 Bihar
20 Implementation of rural electrification works in Kishanganj under DDUGJY Government Infrastructure Projects (Traditional Procurement) 33.00 KV (Kilo Volt) 126.54 Energy Electricity transmission Under Construction North Bihar Power Distribution Company Limited 05-Dec-2016 Bihar
Note: Zero indicates information not available.